Bathroom renovation portal. Useful Tips

Operating instructions for an automatic gas fire extinguishing system. Fire extinguishing installation maintenance

OJSC SIBNEFT-NOYABRSKNEFTEGAZ

TERRITORIAL OIL PRODUCTION PROJECT

"HOLMOGORNEFT"

I N S T R U K C I Z

on the operation of the water system

fire extinguishing unit UPSVG-2 TsPPN-2.

Noyabrsk

2003 year.

OJSC "SIBNEFT - NOYABRSKNEFTEGAZ"

"KHOLMOGORNEFT" TERRITORIAL OIL PRODUCTION PROJECT

APPROVED APPROVED

Chairman of the Trade Union Committee Head of TPDN

TPDN "Kholmogorneft" "Kholmogorneft"

___________ O.F. Yushko _______ S.Yu. Rusakov

"" _______2003 "___" ________ 2003

Chief PCh-130 OGPS-9

THEM. Miroshnichenko

"__" __________2003

I N S T R U K C I Z

on the operation of the water system

fire extinguishing unit UPSVG-2 TsPPN-2.

I.General position.

This instruction was developed on the basis of the "Fire safety rules in Russian Federation"(PPB 01-03) and" Fire safety rules in the oil industry "PPBO-85.

1.1. The head of the workshop, by his order, appoints a person responsible for safe operation water fire extinguishing systems.

1.2. The person responsible for technical operation regularly conducts inspections, checks and tests in accordance with the schedule, together with the service organization of the entire water fire extinguishing system.

II. Purpose and device of water extinguishing.

2.1. The water fire extinguishing system is designed for external extinguishing of buildings and structures of the installation, as well as for supplying water to the tank farm for cooling the tanks by irrigation when oil is ignited in them.

2.2. The installation consists of a ring pipeline with 13 fire hydrants designed by Doroshevsky, located along the perimeter of the UPSVG and the tank farm and connected to the reservoir pressure maintenance system using valves No. 551/1, 551/2, 557, 558, valve assemblies for supplying water through directions.

2.2.1. The water-fire extinguishing system is dry-pipe, laid above the ground with heat traces. On the fire-fighting water supply, valves for air release are installed at elevated turning points, and drains for draining water at lower points.

2.2.2. Block-box of fire pumps - pumps K 100/65 - 2 pcs., For supplying water from firefighters RVS - 1.2 to the fire ring.

2.2.3. Plumbing, fire hydrants, fittings are thermally insulated together with heat traces with mineral wool mats.

2.2.4. All RVS-5000 are equipped with a stationary wall cooling unit, consisting of an irrigation ring and a supply dry pipe. The dry pipe is connected to an annular fire-fighting water pipe through a gate valve. The irrigation ring consists of four parts, each part is supplied with water through a separate supply dry pipe. In addition, a dry pipe was removed for cooling the walls of the tank from mobile equipment through the connecting heads GM-80.

III. Preparation of the fire extinguishing system for work.

3.1. When preparing the fire extinguishing system for operation, it is necessary to check the position of the manual and electric valves:

3.1.1. The gate valves for connecting the fire extinguishing system to the RPM system No. 550, 551/1, 551/2, 552 must always be open.

3.1.2. Electric valves No. 554, 555, 558 and gate valves on bypass lines No. 553, 556, 557 must be closed.

3.1.2. Fire ring valves No. 560, 561, 562, 563, 564, 565, 566, 567, 568 must be open.

3.1.3. All water supply valves for cooling the tanks must be closed:

RVS-5000 No. 1 - No. 569 / 1-572 / 1, 569 / 1d-572 / 1d;

RVS-5000 No. 2 - No. 569 / 2-572 / 2, 569 / 2d-572 / 2d;

RVS-5000 No. 3 - No. 569 / 3-572 / 3, 569 / 3d-572 / 3d;

RVS-5000 No. 4 - No. 569 / 4-572 / 4, 569 / 4d-572 / 4d.

3.1.4. Valves No. 1, 2, 4, and 14 on the fire-fighting VVS-1.2 must be open.

3.2. Check the pressure in the pressure maintenance system, it must be at least 5 kgf / cm 2

IV. The inclusion of the fire extinguishing system in the work.

4.1. To turn on the fire extinguishing system in operation, it is necessary to turn on the K 100/65 pump to fill the system with water.

4.2. The pressure in the system must be maintained at least 5 kgf / cm 2 by adjusting the flow through the gate valves No. 554, 555, 558 at the connection point to the pressure maintenance system.

4.3. In the event of a fire on the RVS-5000, open the valves No. 569-572 of the burning and cooled tanks. If more intensive cooling is required, we connect fire fighting equipment using connection heads GM-80 and open the corresponding valves (No. 569d-572d) of the additionally cooled tank.

4.4. Possible additional cooling of tanks by connecting

to the nearest safely located fire hydrants (PG 1-10)

RUSSIAN JOINT STOCK COMPANY
ENERGY AND ELECTRIFICATION "UES OF RUSSIA"

DEPARTMENT OF SCIENCE AND TECHNOLOGY

TYPICAL INSTRUCTIONS
ON OPERATION OF AUTOMATIC WATER EXTINGUISHING UNITS

RD 34.49.501-95

ORGRES BEST EXPERIENCE SERVICE

MOSCOW 1996

DEVELOPED Joint-stock company "Company for adjustment, improvement of technology
and operation of power plants and networks "ORGRES".

AGREED with the Department of the General Inspection for the Operation of Power Plants
and networks of RAO "UES of Russia" December 28, 1995

REPLACE TI 34-00-046-85.

VALIDITY installed from 01.01.97

In the present Typical instructions the basic requirements for operation are given technological equipment water fire extinguishing installations used at energy enterprises, as well as the procedure for flushing and pressure testing of pipelines of fire extinguishing installations. The scope and sequence of monitoring the state of technological equipment, the timing of the audit of all equipment of fire extinguishing installations are indicated, and basic recommendations for troubleshooting are given.

Responsibility for the operation of fire extinguishing installations has been established, the necessary working documentation and training requirements.

The main safety requirements for the operation of fire extinguishing installations are indicated.

The forms of acts of flushing and pressure testing of pipelines and conducting fire tests are given.

With the release of this Model Instruction, the “Typical instruction for the operation of automatic fire extinguishing installations: TI 34-00-046-85” (Moscow: SPO Soyuztekhenergo, 1985) is no longer valid.

1. INTRODUCTION

1.1. The standard instruction establishes the requirements for the operation of technological equipment for water fire extinguishing installations and is mandatory for managers of energy companies, shop managers and persons appointed responsible for the operation of fire extinguishing installations.

1.2. Technical requirements for the operation of technological equipment of installations foam fire extinguishing are set out in the "Instructions for the operation of fire extinguishing installations using air-mechanical foam" (Moscow: SPO ORGRES, 1997).

1.3. During operation fire alarm automatic installation fire extinguishing (AUP) should be guided by the "Typical instructions for the operation of automatic fire alarm systems at power enterprises" (Moscow: SPO ORGRES, 1996).

The following abbreviations are adopted in this Model Instructions.

UVP - installation of water fire extinguishing,

AUP - automatic fire extinguishing installation,

AUVP - automatic water fire extinguishing installation,

PPS - fire alarm panel,

PUEZ - control panel for electric valves,

PUPN - fire pump control panel,

PI - fire detector,

PN - fire pump,

OK - check valve,

DV - water drencher,

DVM - modernized water drencher,

OPDR - foam-drencher sprinkler.

2. GENERAL INSTRUCTIONS

2.1. Based on this Model Instruction, the organization that performed the adjustment of the AUP technological equipment, together with the power company where this equipment is installed, must develop a local instruction for the operation of technological equipment.
and AUP devices. If the adjustment was carried out by an energy enterprise, then the instructions are developed by the personnel of this enterprise. Local regulations must be developed at least one month in advance
before the acceptance of the AUP into operation.

2.2. The local instruction shall take into account the requirements of this Model Instruction.
and the requirements of factory passports and operating instructions for equipment, instruments and apparatus that are part of the AUVP. Reduction of the requirements set forth in these documents is not allowed.

2.3. The local instruction must be revised at least once every three years and every time after the reconstruction of the AUP or in case of a change in operating conditions.

2.4. Acceptance of AUP into operation should be carried out by representatives of:

energy companies (chairman);

design, installation and commissioning organizations;

state fire supervision.

The work program of the commission and the acceptance certificate must be approved by the main technical
the head of the enterprise.

3. SAFETY MEASURES

3.1. During the operation of technological equipment of water fire extinguishing installations
the personnel of power companies must comply with the relevant safety requirements specified in the PTE, PTB, as well as in the factory passports and operating instructions for a specific
equipment.

3.2. During the maintenance and repair of the AUP, when visiting the premises protected by the AUP, automatic control of a specific distribution pipeline in this direction must be switched to manual (remote) before the last person leaves the room.

3.3. Pressure testing of pipelines with water should be carried out only according to an approved program,
which should include measures to ensure the protection of personnel from a possible rupture of pipelines. Ensure complete removal of air from pipelines. It is prohibited to combine crimping work with other work in the same room. If the pressure testing is carried out by contractors, then the work is carried out according to the permit. The performance of these works by the operational or repair personnel of the power company is documented in a written order.

3.4. Before starting work, personnel involved in pressure testing must be instructed in workplace safety.

3.5. During crimping, no unauthorized persons should be in the room. Pressure testing must be carried out under the supervision of a responsible person.

3.6. Repair work on the technological equipment should be carried out after the pressure is removed from this equipment and the preparation of the necessary organizational and technical measures established by the existing PTB.

4. PREPARATION FOR WORK AND INSPECTION
TECHNICAL CONDITION OF THE FIRE EXTINGUISHING UNIT

4.1. The water fire extinguishing installation consists of:

source of water supply (reservoir, reservoir, city water supply, etc.);

fire pumps (designed for the intake and supply of water to pressure pipelines);

suction pipelines (connecting the water source with fire pumps);

pressure pipelines (from the pump to the control unit);

distribution pipelines (laid within the protected premises);

control units installed at the end of pressure pipelines;

sprinklers.

In addition to the above, based on design solutions, the following can be included in the fire extinguishing installations scheme:

water tank for filling fire pumps;

pneumatic tank for maintaining constant pressure in the network of the fire extinguishing installation;

a compressor for feeding the pneumatic tank with air;

drain taps;

check valves;

dosage washers;

pressure switch;

manometers;

vacuum gauges;

level gauges for measuring the level in tanks and a pneumatic tank;

other signaling, control and automation devices.

The schematic diagram of the water fire extinguishing installation is shown in the figure.

4.2. After graduation installation works suction, pressure and distribution pipelines must be flushed and hydrostatically tested. The results of washing and pressing must be documented in acts (Appendices 1 and 2).

If possible, the effectiveness of the fire extinguishing installation should be checked by organizing the extinguishing of an artificial fire source (Appendix 3).

Schematic diagram of a water fire extinguishing installation:

1 - water storage tank; 2 - fire pump (PN) with electric drive; 3 - pressure pipeline;
4 - suction pipeline; 5 - distribution pipeline; 6 - fire detector (PI);
7 - control unit; 8 - manometer; 9 - check valve (OK)

Notese. Standby fire pump with fittings not shown.

4.3. When flushing pipelines, water should be supplied from their ends towards the control units (in order to prevent clogging of pipes with a smaller diameter) at a speed 15-20% higher than the speed of water in case of fire (determined by calculation or recommendations design organizations). Flushing should be continued until a stable appearance pure water.

If it is impossible to flush individual sections of the pipelines, it is allowed to blow them
dry, clean, compressed air or inert gas.

4.4. Hydraulic testing of pipelines must be carried out under a pressure equal to 1.25 working pressure (P), but not less than P + 0.3 MPa, for 10 minutes.

To disconnect the tested section from the rest of the network, it is necessary to install blind flanges or plugs. It is not allowed to use for this purpose the existing control units, repair valves, etc.

After 10 minutes of testing, the pressure should be gradually reduced to working pressure and a thorough inspection of all welded joints and adjacent areas should be performed.

The pipeline network is considered to have passed the hydraulic test if there are no signs of rupture, leaks and drops in welded joints and on the base metal, visible residual
deformations.

The pressure should be measured with two pressure gauges.

4.5. Flushing and hydraulic testing of pipelines should be carried out under conditions
excluding their freezing.

It is forbidden to backfill open trenches with pipelines that have been exposed to severe frosts, or backfilling of such trenches with frozen soil.

4.6. Automatic water fire extinguishing installations must operate in the automatic start mode. For the period when personnel are in cable facilities (bypass, repair work
etc.) start-up of installations should be transferred to manual (remote) switching on (p. 3.2).

5. MAINTENANCE OF FIRE EXTINGUISHING UNITS

5.1. Organizational activities

5.1.1. Persons responsible for the operation, capital and current repairs technological equipment of the fire extinguishing installation, are appointed by the head of the energy company, who also approves the schedules for technical supervision and equipment repair.

5.1.2. The person responsible for the constant readiness of the technological equipment of the fire extinguishing installation must know well the principle of the device and the procedure for the operation of this equipment,
and also have the following documentation:

project with changes made during the installation and commissioning of the fire extinguishing installation;

factory passports and operating instructions for equipment and devices;

these Model instructions and local instructions for the operation of technological equipment;

acts and protocols of maintenance of installation and adjustment works, as well as testing the work of technological equipment;

schedules of maintenance and repair of technological equipment;

"Log book for the maintenance and repair of the fire extinguishing installation."

5.1.3. Any deviations from the scheme adopted by the project, replacement of equipment, additional
installation of sprinklers or their replacement with sprinklers with a large nozzle diameter must be previously agreed with the design institute - the author of the project.

5.1.4. To monitor the technical condition of the technological equipment of the fire extinguishing installation, a "Register of maintenance and repair of the fire extinguishing installation" should be kept, which should record the date and time of the inspection, who carried out the inspection, the detected faults, their nature and time of their elimination, the time of forced shutdown and activation fire extinguishing installations, carried out by testing the operation of the entire installation or individual equipment. The approximate form of the journal is given in Appendix 4.

At least once a quarter, the chief technical manager of the enterprise must familiarize himself with the contents of the journal on receipt.

5.1.5. To check the readiness and efficiency of the AUVP, a complete audit of the technological equipment of this installation should be carried out once every three years.

During the audit, in addition to the main work, pressure testing of the pressure pipeline is carried out and flushing (or purging) and pressure testing of distribution pipelines (clauses 4.2–4.5) located in the most aggressive environment (dampness, gas contamination, dust) are carried out in two or three directions.

If deficiencies are found, it is necessary to develop measures to ensure complete
their elimination in a short time.

5.1.6. Automatic fire extinguishing installation in accordance with the approved schedule
by the head of the relevant workshop, but at least once every three years, they must be tested (tested) according to a specially developed program with their actual start-up, provided that it is
will not entail a shutdown of technological equipment or the entire production process. During testing on the first and last sprinklers, the water pressure and irrigation intensity should be checked.

Testing should be carried out for 1.5–2 minutes with the inclusion of serviceable drainage devices.

Based on the results of testing, an act or protocol must be drawn up, and the fact of testing itself must be registered in the "Journal of maintenance and repair of the fire extinguishing installation".

5.1.7. Checking the operation of AUVP or certain types of equipment should be carried out during the withdrawal for repair, maintenance of the protected premises and the technological unit.

5.1.8. For storage of spare equipment, equipment parts, as well as accessories,
tools, materials, devices necessary for control and organization renovation works AUVP, a special room must be allocated.

5.1.9. Technical capabilities AUVP should be included in the operational plan for extinguishing the fire
at this power plant. During firefighting trainings, it is necessary to expand the circle of personnel who know the purpose and device of the AUVP, as well as the procedure for activating it.

5.1.10. The personnel servicing the AUVP compressors and pneumatic tanks must be trained and certified in accordance with the requirements of the Gosgortekhnadzor rules.

5.1.11. The person responsible for the operation of the technological equipment of the fire extinguishing installation must organize training with personnel assigned to control the operation and maintenance of this equipment.

5.1.12. In room pumping station AUVP should be posted: instructions on how to turn on pumps and open valves, as well as conceptual and technological diagrams.

5.2. Technical requirements for AUVP

5.2.1. The entrances to the building (room) of the pumping station and the fire extinguishing installation, as well as the approaches to the pumps, pneumatic tank, compressor, control bridles, pressure gauges and other equipment of the fire extinguishing installation, must always be free.

5.2.2. On an operating fire extinguishing installation, it must be sealed in the working
position:

hatches of reservoirs and tanks for storing water supplies;

control units, gate valves and manual cranes;

pressure switch;

drain taps.

5.2.3. After the fire extinguishing installation is triggered, its operability must be fully restored not after 24 hours.

RUSSIAN JOINT STOCKSOCIETYENERGY
AND
ELECTRIFICATIONS « EECRUSSIA»

DEPARTMENTSCIENCEANDTECHNIQUES

TYPICALINSTRUCTIONS
ON
OPERATIONAUTOMATIC
INSTALLATIONS
WATERFIRE FIGHTING

RD 34.49.501-95

ORGRES

Moscow 1996

Designed by Joint-stock company "Firm for adjustment, improvement of technology and operation of power plants and networks" ORGRES ".

Performers YES. A. N. ZAMYSLOV Ivanov, A.S. V. M. KOZLOV STARIKOV

Agreed with the Department of the General Inspection for the Operation of Power Plants and Grids of RAO "UES of Russia" on December 28, 1995

Head N.F. Gorev

Head A.P. BERSENEV

STANDARD OPERATING INSTRUCTIONS FOR AUTOMATIC WATER EXTINGUISHING UNITS

RD 34.49.501-95

Expiration date set

from 01.01.97

This Model Instruction provides the basic requirements for the operation of the technological equipment of water fire extinguishing installations used at power enterprises, as well as the procedure for flushing and pressure testing of pipelines of fire extinguishing installations. The scope and sequence of monitoring the state of technological equipment, the timing of the audit of all equipment of fire extinguishing installations are indicated, and basic recommendations for troubleshooting are given.

Responsibility for the operation of fire extinguishing installations has been established, the necessary working documentation and requirements for personnel training have been provided.

The main safety requirements for the operation of fire extinguishing installations are indicated.

The forms of acts of flushing and pressure testing of pipelines and conducting fire tests are given.

With the release of this Model Instruction, the “Typical instruction for the operation of automatic fire extinguishing installations: TI 34-00-046-85” (Moscow: SPO Soyuztekhenergo, 1985) becomes invalid.

1. INTRODUCTION

1.1. The standard instruction establishes the requirements for the operation of technological equipment for water fire extinguishing installations and is mandatory for managers of power companies, shop managers and persons appointed responsible for the operation of fire extinguishing installations.

1.2. Technical requirements for the operation of technological equipment for foam fire extinguishing installations are set out in the "Instructions for the operation of fire extinguishing installations using air-mechanical foam" (Moscow: SPO ORGRES, 1997).

1.3. When operating a fire alarm of an automatic fire extinguishing system (AUP), one should be guided by the "Standard instruction for the operation of automatic fire alarm systems at power enterprises" (Moscow: SPO ORGRES, 1996).

The following abbreviations are adopted in this Model Instructions.

UVP - installation of water fire extinguishing,

AUP - automatic fire extinguishing installation,

AUVP - automatic water fire extinguishing installation,

PPS - fire alarm panel,

PUEZ - control panel for electric valves,

PUPN - fire pump control panel,

PI - fire detector,

PN - fire pump,

OK - check valve,

DV - water drencher,

DVM - modernized water drencher,

OPDR - foam-drencher sprinkler.

2. GENERAL INSTRUCTIONS

2.1. Based on this Model Instruction, the organization that performed the adjustment of the AUP technological equipment, together with the power company where this equipment is installed, must develop a local operating manual for the technological equipment and AUP devices. If the adjustment was carried out by an energy enterprise, then the instructions are developed by the personnel of this enterprise. The local instruction must be developed at least one month before the AUP is put into operation.

2.2. The local instructions must take into account the requirements of this Model instruction and the requirements of factory passports and instructions for the operation of equipment, instruments and apparatus that are part of the AUVP. Reduction of the requirements set forth in these documents is not allowed.

2.3. The local instruction must be revised at least once every three years and every time after the reconstruction of the AUP or in case of a change in operating conditions.

2.4. Acceptance of AUP into operation should be carried out by representatives of:

energy companies (chairman);

design, installation and commissioning organizations;

state fire supervision.

The commission's work program and acceptance certificate must be approved by the chief technical manager of the enterprise.

3. SAFETY MEASURES

3.1. When operating the technological equipment of water fire extinguishing installations, the personnel of power companies must comply with the relevant safety requirements specified in the PTE, PTB, as well as in the factory passports and operating instructions for specific equipment.

3.2. During the maintenance and repair of the AUP, when visiting the premises protected by the AUP, the automatic control of a particular distribution pipeline in this direction should be switched to manual (remote) until the last person leaves the room.

3.3. Pressure testing of pipelines with water should be carried out only according to an approved program, which should include measures to ensure the protection of personnel from a possible rupture of pipelines. Ensure complete removal of air from pipelines. It is prohibited to combine crimping work with other work in the same room. If the pressure testing is carried out by contractors, then the work is carried out according to the permit. The performance of these works by the operational or repair personnel of the power company is documented in a written order.

3.4. Before starting work, personnel involved in pressure testing must be instructed in workplace safety.

3.5. During crimping, no unauthorized persons should be in the room. Pressure testing must be carried out under the supervision of a responsible person.

3.6. Repair work on the technological equipment should be carried out after the pressure is removed from this equipment and the preparation of the necessary organizational and technical measures established by the existing PTB.

4. PREPARATION FOR WORK AND CHECKING THE TECHNICAL CONDITION OF THE FIRE EXTINGUISHING UNIT

4.1. The water fire extinguishing installation consists of:

source of water supply (reservoir, reservoir, city water supply, etc.);

fire pumps (designed for the intake and supply of water to pressure pipelines);

suction pipelines (connecting the water source with fire pumps);

pressure pipelines (from the pump to the control unit);

distribution pipelines (laid within the protected premises);

control units installed at the end of pressure pipelines;

sprinklers.

In addition to the above, based on design solutions, the following can be included in the fire extinguishing installations scheme:

water tank for filling fire pumps;

pneumatic tank for maintaining constant pressure in the network of the fire extinguishing installation;

a compressor for feeding the pneumatic tank with air;

drain taps;

check valves;

dosage washers;

pressure switch;

manometers;

vacuum gauges;

level gauges for measuring the level in tanks and a pneumatic tank;

other signaling, control and automation devices.

The schematic diagram of the water fire extinguishing installation is shown in the figure.

4.2. After the completion of the installation work, the suction, pressure and distribution pipelines must be flushed and subjected to hydraulic tests. The results of flushing and pressure testing must be documented in acts (attachments and).

If possible, the effectiveness of the fire extinguishing installation should be checked by organizing the extinguishing of an artificial fire source (appendix).

4.3. When flushing pipelines, water should be supplied from their ends towards the control units (in order to prevent clogging of pipes with a smaller diameter) at a speed 15 - 20% higher than the speed of water in a fire (determined by calculation or recommendations of design organizations). Flushing should be continued until clean water is consistently produced.

If it is impossible to flush individual sections of pipelines, it is allowed to blow them with dry, clean, compressed air or inert gas.

Schematic diagram of a water fire extinguishing installation:

1 - water storage tank; 2 - fire pump (PN) with electric drive; 3 - pressure pipeline; 4 - suction pipeline; 5 - distribution pipeline; 6 - fire detector (PI); 7 - control unit; 8 - manometer; 9 - check valve (OK)

Note. The standby fire pump with fittings is not shown.

4.4. Hydraulic testing of pipelines must be carried out under a pressure equal to 1.25 working pressure (P), but not less than P + 0.3 MPa, for 10 minutes.

To disconnect the tested section from the rest of the network, it is necessary to install blind flanges or plugs. It is not allowed to use existing control units, repair valves, etc. for this purpose.

After 10 minutes of testing, the pressure should be gradually reduced to working pressure and a thorough inspection of all welded joints and adjacent areas should be performed.

The pipeline network is considered to have passed the hydraulic test if no signs of rupture, leaks and drops in welded joints and on the base metal, visible permanent deformations are found.

The pressure should be measured with two pressure gauges.

4.5. Flushing and hydraulic testing of pipelines should be carried out under conditions that exclude their freezing.

It is prohibited to backfill open trenches with pipelines exposed to severe frosts, or backfill such trenches with frozen soil.

4.6. Automatic water fire extinguishing installations must operate in the automatic start mode. For the period when personnel are in cable facilities (bypass, repair work, etc.), the start-up of installations should be switched to manual (remote) switching (p.).

5. MAINTENANCE OF FIRE EXTINGUISHING UNITS

5.1 ... Organizational activities

5.1.1. Persons responsible for the operation, overhaul and current repairs of the technological equipment of the fire extinguishing installation are appointed by the head of the energy company, who also approves the schedules for technical supervision and equipment repair.

5.1.2. The person responsible for the constant readiness of the technological equipment of the fire extinguishing installation must know well the principle of the device and the procedure for the operation of this equipment, and also have the following documentation:

project with changes made during the installation and commissioning of the fire extinguishing installation;

factory passports and operating instructions for equipment and devices;

this Model Instruction and local operating instructions for process equipment;

acts and protocols of installation and commissioning works, as well as testing of technological equipment;

schedules of maintenance and repair of technological equipment;

"Log book for the maintenance and repair of the fire extinguishing installation."

5.1.3. Any deviations from the scheme adopted by the project, replacement of equipment, additional installation sprinklers or their replacement by sprinklers with a large nozzle diameter must be previously agreed with the design institute - the author of the project.

5.1.4. To monitor the technical condition of the technological equipment of the fire extinguishing installation, a "Register of maintenance and repair of the fire extinguishing installation" should be kept, which should record the date and time of the inspection, who carried out the inspection, the detected faults, their nature and time of their elimination, the time of forced shutdown and activation fire extinguishing installations, carried out by testing the operation of the entire installation or individual equipment. The approximate form of the journal is given in the appendix.

At least once a quarter, the chief technical manager of the enterprise must familiarize himself with the contents of the journal on receipt.

5.1.5. To check the readiness and efficiency of the AUVP, a complete audit of the technological equipment of this installation should be carried out once every three years.

During the audit, in addition to the main work, pressure testing of the pressure pipeline is carried out and flushing (or purging) and pressure testing of distribution pipelines (pp. -) are carried out in two or three directions, which are in the most aggressive environment (dampness, gas pollution, dust).

If deficiencies are found, it is necessary to develop measures to ensure their complete elimination in a short time.

5.1.6. An automatic fire extinguishing installation in accordance with the schedule approved by the head of the relevant workshop, but at least once every three years, must be tested (tested) according to a specially developed program with the actual start-up of them, provided that this does not entail a shutdown of the technological equipment or all the production process. During testing on the first and last sprinklers, the water pressure and irrigation intensity should be checked.

Testing should be carried out for 1.5 - 2 minutes with the inclusion of serviceable drainage devices.

Based on the results of testing, an act or protocol must be drawn up, and the fact of testing itself must be registered in the "Journal of maintenance and repair of the fire extinguishing installation".

5.1.7. Checking the operation of AUVP or certain types of equipment should be carried out during the withdrawal for repair, maintenance of the protected premises and the technological unit.

5.1.8. For storage of spare equipment, equipment parts, as well as fixtures, tools, materials, devices necessary for the control and organization of repair work of AUVP, a special room should be allocated.

5.1.9. The technical capabilities of AUVP should be included in the operational plan for extinguishing a fire at a given power plant. During firefighting trainings, it is necessary to expand the circle of personnel who know the purpose and device of the AUVP, as well as the procedure for activating it.

5.1.10. The personnel servicing the AUVP compressors and pneumatic tanks must be trained and certified in accordance with the requirements of the Gosgortekhnadzor rules.

5.1.11. The person responsible for the operation of the technological equipment of the fire extinguishing installation must organize training with personnel assigned to control the operation and maintenance of this equipment.

5.1.12. In the room of the AUVP pumping station, the following should be posted: instructions on how to turn on the pumps and open shut-off valves, as well as basic and technological diagrams.

5.2 ... Technical requirements for AUVP

5.2.1. The entrances to the building (room) of the pumping station and the fire extinguishing installation, as well as the approaches to the pumps, pneumatic tank, compressor, control units, pressure gauges and other equipment of the fire extinguishing installation, must always be free.

5.2.2. On an operating fire extinguishing installation, the following must be sealed in working position:

hatches of reservoirs and tanks for storing water supplies;

control units, gate valves and manual cranes;

pressure switch;

drain taps.

5.2.3. After the fire extinguishing installation has been triggered, its operability must be fully restored no later than 24 hours later.

5.3 ... Water storage tanks

5.3.1. Checking the water level in the tank should be carried out daily with registration in the "Log book of maintenance and repair of the fire extinguishing installation".

If the water level drops due to vapors, it is necessary to add water, if there are leaks, locate the damage to the reservoir and repair the leaks.

5.3.2. The correct operation of the automatic level gauge in the tank should be checked at least once every three months at positive temperatures, monthly - at negative temperatures and immediately in case of doubts about the correct operation of the level gauge.

5.3.3. The tanks must be closed for unauthorized access and sealed, the integrity of the seal is checked during the inspection of the equipment, but at least once a quarter.

5.3.4. The water in the tank should not contain mechanical impurities that could clog pipelines, metering washers and sprinklers.

5.3.5. To prevent decay and blooming of water, it is recommended to disinfect it with bleach at the rate of 100 g of lime per 1 m3 of water.

5.3.6. It is necessary to change the water in the tank annually in the fall. When changing the water, the bottom and inner walls of the tank are cleaned of dirt and build-up, the damaged paint is restored or completely renewed.

5.3.7. Before the onset of frost near buried tanks, the gap between the upper and lower hatch covers must be filled with insulating material.

5.4 ... Suction pipeline

5.4.1. Once a quarter, the condition of the bushings, shut-off valves, measuring instruments and a water intake well.

5.4.2. Before the onset of frost, the fittings in the water intake well must be inspected, repaired if necessary, and the well must be insulated.

5.5 ... Pumping station

5.5.1. Before testing the pumps it is necessary to check: the tightening of the oil seals; the level of lubrication in the bearing tubs; correct tightening of foundation bolts, pump cover nuts and bearings; suction-side piping connections and the pumps themselves.

5.5.2. Once a month, pumps and other equipment of the pumping station should be inspected, cleaned of dust and dirt.

5.5.3. Each fire pump must be turned on at least twice a month to create the required pressure, which is recorded in the operational log.

5.5.4. At least once a month, the reliability of the transfer of all fire pumps to the main and reserve power supply should be checked with the registration of the results in the operational log.

5.5.5. If there is a special tank for filling the pumps with water, the latter must be inspected and painted annually.

5.5.6. Once every three years, pumps and motors according to p. of this Model Instruction must undergo an audit, during which all existing deficiencies are eliminated.

Repair and replacement of worn out parts, check of oil seals are carried out as needed.

5.5.7. The pumping station must be kept clean. In the absence of duty, it must be locked. One of the spare keys must be kept on the control panel, which must be indicated on the door.

5.6 ... Pressure and distribution pipelines

5.6.1. Once a quarter, it is necessary to check:

absence of leaks and deflections of pipelines;

the presence of a constant slope (not less than 0.01 for pipes with a diameter of up to 50 mm and 0.005 for pipes with a diameter of 50 mm and more);

condition of pipeline fasteners;

lack of contact with electric wires and cables;

condition of painting, absence of dirt and dust.

Discovered deficiencies that could affect the reliability of the installation should be eliminated immediately.

5.6.2. The pressure pipeline must be always ready for action, i.e. filled with water and under operating pressure.

5.7 ... Control units and valves

5.7.1. For AUVP transformers and cable structures in locking and starting devices, steel reinforcement electrified gate valves with automatic start of grade 30s 941nzh should be used; 30s 986nzh; 30s 996nzh with a working pressure of 1.6 MPa, repair valves with a manual drive brand 30s 41nzh with a working pressure of 1.6 MPa.

5.7.2. The state of the control units and valves, the presence of a seal, the pressure values ​​before and after the control units must be monitored at least once a month.

5.7.3. An inspection should be carried out once every six months electrical circuit actuation of the control unit with its automatic activation from the fire detector when the valve is closed.

5.7.4. The installation site of the control unit should be well lit, inscriptions on pipelines or special stencils (unit number, protected area, type of sprinklers and their number) should be made with indelible bright paint and clearly visible.

5.7.5. Any damage to valves, valves and check valves that can affect the reliability of the fire extinguishing installation must be eliminated immediately.

5.8 ... Sprinklers

5.8.1. As water sprinklers for automatic fire extinguishing transformers, sprinklers OPDR-15 are used with a working water pressure in front of the sprinklers in the range of 0.2 - 0.6 MPa; for automatic fire extinguishing of cable structures, sprinklers DV, DVM with a working pressure of 0.2 - 0.4 MPa are used.

5.8.2. When inspecting equipment switchgears, but at least once a month, sprinklers should be inspected and cleaned of dust and dirt. If a malfunction or corrosion is detected, measures must be taken to eliminate them.

5.8.3. During repair work, sprinklers must be protected from plaster and paint (for example, plastic or paper caps, etc.). Traces of paint and mortar found after repair must be removed.

5.8.5. To replace faulty or damaged sprinklers, a reserve of 10 - 15% must be created the total installed sprinklers.

5.9 ... Pneumatic tank and compressor

5.9.1. The inclusion of the pneumatic tank in operation should be carried out in the following sequence:

fill the pneumatic tank with water to about 50% of its volume (control the level on the water gauge glass);

turn on the compressor or open the valve on the compressed air line;

raise the pressure in the pneumatic tank to the working pressure (controlled by the pressure gauge), then connect the pneumatic tank to the pressure pipeline, creating a working pressure in it.

5.9.2. An external inspection of the pneumatic tank should be carried out daily, check the water level and air pressure in the pneumatic tank. When the air pressure drops by 0.05 MPa (in relation to the working one), it is pumped up.

The compressor is tested at idle speed once a week.

5.9.3. Maintenance pneumatic tank and compressor, carried out once a year, includes:

emptying, inspecting and cleaning the pneumatic tank:

removal and testing of the safety valve at the stand (in case of malfunction, replace with a new one);

painting of the surface of the pneumatic tank (indicate the date of repair on the surface);

detailed inspection of the compressor (replace worn parts and fittings);

fulfillment of all others technical requirements provided by the factory passports and operating instructions for the pneumatic tank and compressor.

5.9.4. It is prohibited to turn off the pneumatic tank from the fire extinguishing installation diagram.

5.9.5. The examination of the pneumatic tank is carried out by a special commission with the participation of representatives of the Gosgortechnadzor, local authorities State fire supervision and this energy company.

Note. The compressor should only be started up manually. In this case, it is necessary to monitor the level in the pneumatic tank, since when the compressor is automatically turned on, water can be squeezed out of the pneumatic tank and even from the network by air.

5.10 ... Pressure gauges

5.10.1. The correctness of the readings of the pressure gauges installed on the pneumatic tanks should be checked once a month, installed on the pipelines - once every six months.

5.10.2. Full check at the fire extinguishing installation, all pressure gauges with their sealing or stamping must be carried out annually in accordance with the current regulation.

6. ORGANIZATION AND REQUIREMENTS FOR REPAIR WORKS

6.1. During the repair of the technological equipment of the fire extinguishing installation, one should, first of all, be guided by the requirements of the passport, the instructions of the plant for the operation of specific equipment, the requirements of the relevant standards and technical conditions, as well as the requirements of this Model Instruction.

6.2. When replacing a section of a pipeline at a bend minimum radius internal bending curve steel pipes when bending them in a cold state, it should be at least four outer diameters, in a hot state - at least three.

The bent part of the pipe must be free of folds, cracks or other defects. Ovality at bending points is allowed no more than 10% (determined by the ratio of the difference between the largest and smallest outer diameters of the bent pipe to the outer diameter of the pipe before the bend).

6.3. The difference in wall thickness and displacement of the edges of abutting pipes and pipeline parts should not exceed 10% of the wall thickness and should not be more than 3 mm.

6.4. Before welding, the edges of the pipe ends to be welded and the surfaces adjacent to them must be cleaned of rust and dirt to a width of at least 20 mm.

6.5. Welding of each joint must be performed without interruption until the entire joint is fully welded.

6.6. The welded joint of pipes should be rejected if the following defects are found:

cracks emerging on the surface of the seam or base metal in the welding zone;

sagging or undercuts in the zone of transition from base metal to deposited metal;

burn-throughs;

irregularities weld in width and height, as well as its deviations from the axis.

6.7. In especially damp rooms with a chemically active environment, the pipe fastening structures must be made of steel profiles with a thickness of at least 4 mm. Piping and fastening structures must be covered with protective varnish or paint.

6.8. Pipeline connections for open installation should be located outside walls, partitions, ceilings and other building structures of buildings.

6.9. Fastening of pipelines to building structures of buildings should be carried out with normalized supports and hangers. Welding of pipelines directly to metal structures buildings and structures, as well as elements of technological equipment are not allowed.

6.10. Welding of supports and hangers to building structures should be carried out without weakening them mechanical strength.

6.11. Sagging and bending of pipelines are not allowed.

6.12. Each pipe bend over 0.5 m in length must be secured. The distance from the hangers to the welded and threaded pipe joints must be at least 100 mm.

6.13. Newly installed sprinklers must be cleaned of preservative grease and checked with a hydraulic pressure of 1.25 MPa (12.5 kgf / cm2) for 1 minute.

The average service life of sprinklers is determined at least 10 years.

6.14. The performance of the sprinklers DV, DVM and OPDR-15 is given in table. ...

Table 1

Outlet diameter, mm

Sprinkler capacity, l / s, at pressure MPa

DV-10 and DVM-10

table 2

Probable causes

Water does not come out of the sprinklers, the pressure gauge shows normal pressure

Valve closed

Open the latch

Check valve stuck

Open the non-return valve

Clogged pipeline

Clean pipeline

Sprinklers are clogged

Eliminate clogging

Water does not come out of the sprinklers, the pressure gauge does not show pressure

The fire pump did not start working

Turn on the fire pump

The valve on the pipeline on the suction side of the fire pump is closed

Open the latch

Air is leaking on the suction side of the fire pump

Troubleshoot connection problems

Wrong direction of rotation of the rotor

Switch motor phases

The valve in the other direction is accidentally open

Close the valve in the other direction

Leakage of water through welded seams, at the points of connection of control units and sprinklers

Poor welding

Check the quality of welds

Gasket worn out

Replace the gasket

Tightening bolts loosened

Tighten the bolts

_________________________________________________________________________

and _______________________________________________________________________

_________________________________________________________________________

made this act in that the pipelines _____________________________

_________________________________________________________________________

(unit name, section no.)

Special Notes: ___________: ____________________________________________

_________________________________________________________________________

_________________________________________________________________________

_________________________________________________________________________

Commission members:

(surname) (signature)

Mounting

(surname) (signature)

Fire department

(power plant, substation)

We, the undersigned members of the Commission, composed of:

1. From the customer _____________________________________________________________

(representative from the customer, full name, position)

2. From the installation (commissioning) organization _____________________________________

___________________________________________________________________________

(representative from the installation organization, full name, position)

3. From the fire department ______________________________________________________

___________________________________________________________________________

(representative from the fire department, full name, position)

4. _________________________________________________________________________

___________________________________________________________________________

___________________________________________________________________________

drew up this act in that fire tests were carried out in

___________________________________________________________________________

(name of the tested area)

Artificial fires with a size of ____________________________ m2 with combustible material ________________________________________________________________

As a result of the test, the time was established:

setting fire to the fire ___________________________________________ (h, min)

operation of the installation _________________________________________ (h, min)

appearance of water from the foam generator ________________________________ (h, min)

During the firing tests, the installation worked, the room is full

foam for _______________ min

Commission members:

Customer _________________________ _____________________

(surname) (signature)

Mounting

organization _________________________ _____________________

(surname) (signature)

Fire department

security _________________________ _____________________

(surname, position) (signature)

The operation of fire automation installations is understood as their use for detecting or extinguishing fires, as well as their maintenance and repair. When operating AUP, APS, a set of measures is carried out that provide:

technically correct use installations, i.e. application when detecting or extinguishing a fire, in extinguishing mode;

correct storage;

timely and high-quality maintenance in order to maintain the unit in good and efficient condition;

timely and high-quality repairs;

Maintenance is understood as a set of works that provides control technical condition, extending the service life. Maintenance activities are divided into four groups:

preparation of the installation for use after operation or repair, including refueling and loading operations (replacement of triggered or damaged sprinklers, etc.);

control of technical condition;

prevention;

current repairs in order to maintain the reliability and durability of installations.

Monitoring of the technical condition is carried out in order to assess the ability of installations to perform specified functions. This ability is evaluated by the values ​​of certain parameters. If the values ​​of these parameters correspond to the rated values, the installation is considered to be in good working order.

In case of deviation from the norms, the installation is faulty, because it cannot provide satisfactory performance given functions... Thus, monitoring the state of installations is reduced to compiling true ones, i.e. measured at the installation, values, parameters with their nominal values. As a result of the comparison, a conclusion is made about the technical condition of the installation and the possibility of its further use.

Maintenance is divided into daily, monthly, quarterly, and annual. With daily maintenance, the following scope of work is carried out:

monitoring the state of the pipeline painting;

control over adherence to permissible distances (no more than two meters) from sprinklers to stored materials;

external examination of control units (control and launch units, valves);

check on pressure gauges above and below the control and launch unit (the difference should not exceed 0.05);

operation of pumps, compressor in accordance with the instructions (passports) of the manufacturers. The results of the inspection for each item are recorded in the log book "plant operation".

With monthly maintenance, daily maintenance work is carried out, as well as the following operations:

inspection and maintenance work related to the electrical equipment of installations;

checking the voltage of the main and backup power supplies, inputs to automatic switches, inputs of automatic switches in the signaling circuit;

checking the performance of electrical circuits in remote and automatic modes;

inspection and preventive work on all communications of installations

check of pumps and its fittings, pressure - according to the readings of manometers;

check of control and starting devices.

Quarterly maintenance includes monthly maintenance operations, in addition, the following works are performed:

checking the condition and fastening of the pipeline and sprinklers;

checking the work of ЭКМ according to the control pressure gauge;

turning the shafts of the electric motors of the pumps by hand.

The annual includes measures for quarterly maintenance and in addition to this:

tightness test of check valves and gate valves;

inspection and examination of instrumentation within the time frame specified in the factory instructions;

replacement or repair of worn parts;

random check of sprinkler fluid loss;

measurement of the resistance of the ground loop.

In addition, there are maintenance jobs that must be performed every 3 years. These include:

annual maintenance operations;

elimination of leaks in the system, repair of equipment fasteners;

tinting equipment;

repair of grounding devices;

measurement of drive insulation of installations;

revision of pumps, valves;

flushing the system.

INSTRUCTIONS FOR USE AUP.

GENERAL INSTRUCTIONS

Acceptance of AUP into operation should be carried out by representatives of:

energy companies (chairman);

design, installation and commissioning organizations;

state fire supervision.

The commission's work program and acceptance certificate must be approved by the chief technical manager of the enterprise.

SECURITY MEASURES

When operating the technological equipment of water fire extinguishing installations, the personnel of power companies must comply with the relevant safety requirements specified in the PTE, PTB, as well as in the factory passports and operating instructions for specific equipment.

During the maintenance and repair of the AUP, when visiting the premises protected by the AUP, the automatic control of a particular distribution pipeline in this direction should be switched to manual (remote) until the last person leaves the room.

Pressure testing of pipelines with water should be carried out only according to an approved program, which should include measures to ensure the protection of personnel from a possible rupture of pipelines. Ensure complete removal of air from pipelines. It is prohibited to combine crimping work with other work in the same room. If the pressure testing is carried out by contractors, then the work is carried out according to the permit. The performance of these works by the operational or repair personnel of the power company is documented in a written order.

Before starting work, personnel involved in pressure testing must be instructed in workplace safety.

During crimping, no unauthorized persons should be in the room. Pressure testing must be carried out under the supervision of a responsible person.

Repair work on the technological equipment should be carried out after the pressure is removed from this equipment and the preparation of the necessary organizational and technical measures established by the existing PTB.

PREPARATION FOR WORK AND CHECKING THE TECHNICAL CONDITION

FIRE EXTINGUISHING UNITS

The foam fire extinguishing installation consists of:

a source of foam supply (reservoir);

fire pumps (designed for intake and supply of solution to pressure pipelines);

suction pipelines (connecting the water source with fire pumps);

pressure pipelines (from the pump to the control unit);

distribution pipelines (laid within the protected premises);

control units installed at the end of pressure pipelines;

sprinklers.

In addition to the above, based on design solutions, the following can be included in the fire extinguishing installations scheme:

a tank with a foam concentrate solution for filling fire pumps;

pneumatic tank for maintaining constant pressure in the network of the fire extinguishing installation;

a compressor for feeding the pneumatic tank with air;

drain taps;

check valves;

dosage washers;

pressure switch;

manometers;

vacuum gauges;

level gauges for measuring the level in tanks and a pneumatic tank;

other signaling, control and automation devices.

After the completion of the installation work, the suction, pressure and distribution pipelines must be flushed and subjected to hydraulic tests. The results of flushing and pressure testing must be documented.

If possible, the effectiveness of the fire extinguishing installation should be checked by organizing the extinguishing of an artificial fire source.

When flushing pipelines, water should be supplied from their ends towards the control units (in order to prevent clogging of pipes with a smaller diameter) at a speed 15-20% higher than the solution speed in case of fire (determined by calculation or recommendations of design organizations). Flushing should be continued until clean water is consistently produced. If it is impossible to flush individual sections of pipelines, it is allowed to blow them with dry, clean, compressed air or inert gas.

Hydraulic testing of pipelines must be carried out under a pressure equal to 1.25 working pressure (P), but not less than P + 0.3 MPa, for 10 minutes.

To disconnect the tested section from the rest of the network, it is necessary to install blind flanges or plugs. It is not allowed to use for this purpose the existing control units, repair valves, etc.

After 10 minutes of testing, the pressure should be gradually reduced to working pressure and a thorough inspection of all welded joints and adjacent areas should be performed.

The pipeline network is considered to have passed the hydraulic test if no signs of rupture, leaks and drops in welded joints and on the base metal, visible permanent deformations are found.

The pressure should be measured with two pressure gauges.

Flushing and hydraulic testing of pipelines should be carried out under conditions that exclude their freezing.

It is prohibited to backfill open trenches with pipelines exposed to severe frosts, or backfill such trenches with frozen soil.

Automatic water fire extinguishing installations must operate in the automatic start mode. For the period when personnel are in cable facilities (bypass, repair work, etc.), the start-up of installations should be switched to manual (remote) switching.

MAINTENANCE OF FIRE-FIGHTING UNITS

Persons responsible for the operation, overhaul and current repairs of the technological equipment of the fire extinguishing installation are appointed by the head of the energy company, who also approves the schedules for technical supervision and equipment repair.

The person responsible for the constant readiness of the technological equipment of the fire extinguishing installation must know well the principle of the device and the procedure for the operation of this equipment, and also have the following documentation:

project with changes made during the installation and commissioning of the fire extinguishing installation;

factory passports and operating instructions for equipment and devices;

this Model Instruction and local operating instructions for process equipment;

acts and protocols of installation and commissioning works, as well as testing of technological equipment;

schedules of maintenance and repair of technological equipment;

"Log book for the maintenance and repair of the fire extinguishing installation."

Any deviations from the scheme adopted by the project, replacement of equipment, additional installation of sprinklers or their replacement with sprinklers with a large nozzle diameter must be previously agreed with the design institute - the author of the project.

To monitor the technical condition of the technological equipment of the fire extinguishing installation, a "Register of maintenance and repair of the fire extinguishing installation" should be kept, which should record the date and time of the inspection, who carried out the inspection, the detected faults, their nature and time of their elimination, the time of forced shutdown and activation fire extinguishing installations, carried out by testing the operation of the entire installation or individual equipment.

At least once a quarter, the chief technical manager of the enterprise must familiarize himself with the contents of the journal on receipt.

To check the readiness and efficiency of the AUVP, a complete audit of the technological equipment of this installation should be carried out once every three years.

During the audit, in addition to the main work, pressure testing of the pressure pipeline is carried out and flushing (or purging) and pressure testing of distribution pipelines located in the most aggressive environment (dampness, gas pollution, dust) are carried out in two or three directions.

If deficiencies are found, it is necessary to develop measures to ensure their complete elimination in a short time.

An automatic fire extinguishing installation in accordance with the schedule approved by the head of the relevant workshop, but at least once every three years, must be tested (tested) according to a specially developed program with the actual start-up of them, provided that this does not entail a shutdown of the technological equipment or all the production process. During testing on the first and last sprinklers, the water pressure and irrigation intensity should be checked.

Testing should be carried out with a duration of 1.5-2 minutes with the inclusion of serviceable drainage devices.

Based on the results of testing, an act or protocol must be drawn up, and the fact of testing itself must be registered in the "Journal of maintenance and repair of the fire extinguishing installation".

Checking the operation of AUVP or certain types of equipment should be carried out during the withdrawal for repair, maintenance of the protected premises and the technological unit.

For storage of spare equipment, equipment parts, as well as fixtures, tools, materials, devices necessary for the control and organization of repair work of AUVP, a special room should be allocated.

The technical capabilities of AUVP should be included in the operational plan for extinguishing a fire at a given power plant. During firefighting trainings, it is necessary to expand the circle of personnel who know the purpose and device of the AUVP, as well as the procedure for activating it.

The personnel servicing the AUVP compressors and pneumatic tanks must be trained and certified in accordance with the requirements of the Gosgortekhnadzor rules.

The person responsible for the operation of the technological equipment of the fire extinguishing installation must organize training with personnel assigned to control the operation and maintenance of this equipment.

In the room of the AUVP pumping station, the following should be posted: instructions on how to turn on the pumps and open the shut-off valves, as well as basic and technological diagrams.

The entrances to the building (room) of the pumping station and the fire extinguishing installation, as well as the approaches to the pumps, pneumatic tank, compressor, control units, pressure gauges and other equipment of the fire extinguishing installation, must always be free.

On an operating fire extinguishing installation, the following must be sealed in working position:

hatches of reservoirs and tanks for storing water supplies;

control units, gate valves and manual cranes;

pressure switch;

drain taps.

After the fire extinguishing installation is triggered, its operability must be fully restored not after 24 hours.

Checking the water level in the tank should be carried out daily with registration in the "Log book of maintenance and repair of the fire extinguishing installation."

The correct operation of the automatic level gauge in the tank should be checked at least once every three months at positive temperatures, monthly - at negative temperatures and immediately in case of doubts about the correct operation of the level gauge.

The tanks must be closed for unauthorized access and sealed, the integrity of the seal is checked during the inspection of the equipment, but at least once a quarter.

The water in the tank should not contain mechanical impurities that could clog pipelines, metering washers and sprinklers.

To prevent decay and blooming of water, it is recommended to disinfect it with bleach at the rate of 100 g of lime per 1 m of water.

Replace the water in the tank annually at autumn time... When changing the water, the bottom and inner walls of the tank are cleaned of dirt and build-up, the damaged paint is restored or completely renewed.

Before the onset of frost near buried tanks, the gap between the upper and lower hatch covers must be filled with insulating material.

Once a quarter, the condition of the bushings, shut-off valves, measuring instruments and the water intake well is checked.

Before the onset of frost, the fittings in the water intake well must be inspected, repaired if necessary, and the well must be insulated.

Before testing the pumps it is necessary to check: the tightening of the oil seals; the level of lubrication in the bearing tubs; correct tightening of foundation bolts, pump cover nuts and bearings; suction-side piping connections and the pumps themselves.

Once a month, pumps and other equipment of the pumping station should be inspected, cleaned of dust and dirt.

Each fire pump must be turned on at least twice a month to create the required pressure, which is recorded in the operational log.

At least once a month, the reliability of the transfer of all fire pumps to the main and reserve power supply should be checked with the registration of the results in the operational log.

If there is a special tank for filling the pumps with water, the latter must be inspected and painted annually.

Once every three years, pumps and motors, in accordance with clause 5.1.5 of this Standard Instruction, must undergo an audit, during which all existing deficiencies are eliminated. Repair and replacement of worn out parts, check of oil seals are carried out as necessary.

The pumping station must be kept clean. In the absence of duty, it must be locked. One of the spare keys must be kept on the control panel, which must be indicated on the door.

Once a quarter, it is necessary to check:

absence of leaks and deflections of pipelines;

the presence of a constant slope (not less than 0.01 for pipes with a diameter of up to 50 mm and 0.005 for pipes with a diameter of 50 mm and more);

condition of pipeline fasteners;

lack of contact with electric wires and cables;

condition of painting, absence of dirt and dust.

Discovered deficiencies that could affect the reliability of the installation should be eliminated immediately.

The pressure pipeline must be constantly ready for action, i.e. filled with water and under operating pressure.

For AUP of transformers and cable structures in locking and starting devices, steel fittings, electrified valves with automatic start of grade 30s 941nzh should be used; 30s 986nzh; 30s 996nzh with a working pressure of 1.6 MPa, repair valves with manual drive grade 30s 41nzh with a working pressure of 1.6 MPa.

The state of the control units and valves, the presence of a seal, the pressure values ​​before and after the control units must be monitored at least once a month.

Once every six months, the electrical circuit of the control unit actuation should be checked with its automatic activation from the fire detector when the valve is closed.

The installation site of the control unit should be well lit, inscriptions on pipelines or special stencils (unit number, protected area, type of sprinklers and their number) should be made with indelible bright paint and clearly visible.

Any damage to valves, valves and non-return valves that could affect the reliability of the fire extinguishing installation must be repaired immediately.

As water sprinklers for automatic fire extinguishing of transformers, sprinklers OPDR-15 are used with a working water pressure in front of the sprinklers in the range of 0.2-0.6 MPa; for automatic fire extinguishing of cable structures, sprinklers DV, DVM with a working pressure of 0.2-0.4 MPa are used.

When inspecting switchgear equipment, but at least once a month, the sprinklers must be inspected and cleaned of dust and dirt. If a malfunction or corrosion is detected, measures must be taken to eliminate them.

During repair work, sprinklers must be protected from plaster and paint (for example, plastic or paper caps, etc.). Traces of paint and mortar found after repair must be removed.

It is forbidden to install plugs and plugs instead of faulty sprinklers.

To replace faulty or damaged sprinklers, a reserve of 10-15% of the total number of installed sprinklers must be created.

The inclusion of the pneumatic tank in operation should be carried out in the following sequence:

fill the pneumatic tank with water to about 50% of its volume (control the level on the water gauge glass);

turn on the compressor or open the valve on the compressed air line;

raise the pressure in the pneumatic tank to the working pressure (controlled by the pressure gauge), then connect the pneumatic tank to the pressure pipeline, creating a working pressure in it.

An external inspection of the pneumatic tank should be carried out daily, check the water level and air pressure in the pneumatic tank. When the air pressure drops by 0.05 MPa (in relation to the working one), it is pumped up.

The compressor is tested at idle speed once a week.

Maintenance of the pneumatic tank and compressor, carried out once a year, includes:

emptying, inspection and cleaning of the pneumatic tank;

removal and testing of the safety valve at the stand (in case of malfunction, replace with a new one);

painting of the surface of the pneumatic tank (indicate the date of repair on the surface);

detailed inspection of the compressor (replace worn parts and fittings);

fulfillment of all other technical requirements stipulated by the factory passports and operating instructions for the pneumatic tank and compressor.

It is prohibited to turn off the pneumatic tank from the fire extinguishing installation diagram.

The inspection of the pneumatic tank is carried out by a special commission with the participation of representatives of the Gosgortekhnadzor, local authorities of the State Fire Supervision and this energy company.

The correctness of the readings of the pressure gauges installed on the pneumatic tanks should be checked once a month, installed on the pipelines - once every six months.

A complete check at the fire extinguishing installation of all pressure gauges with their sealing or stamping must be carried out annually in accordance with the current regulation.

ORGANIZATION AND REQUIREMENTS FOR REPAIR WORKS

During the repair of the technological equipment of the fire extinguishing installation, one should, first of all, be guided by the requirements of the passport, the instructions of the plant for the operation of specific equipment, the requirements of the relevant standards and technical conditions, as well as the requirements of this manual.

When replacing a section of a pipeline on a bend, the minimum radius of the internal bending curve of steel pipes should be at least four outer diameters when bending them in a cold state, and at least three outer diameters in a hot state.

The bent part of the pipe must be free of folds, cracks or other defects. Ovality at bending points is allowed no more than 10% (determined by the ratio of the difference between the largest and smallest outer diameters of the bent pipe to the outer diameter of the pipe before the bend).

The difference in wall thickness and displacement of the edges of abutting pipes and pipeline parts should not exceed 10% of the wall thickness and should not be more than 3 mm.

Before welding, the edges of the pipe ends to be welded and the surfaces adjacent to them must be cleaned of rust and dirt to a width of at least 20 mm.

Welding of each joint must be performed without interruption until the entire joint is fully welded.

The welded joint of pipes should be rejected if the following defects are found:

cracks emerging on the surface of the seam or base metal in the welding zone;

sagging or undercuts in the zone of transition from base metal to deposited metal;

burn-throughs;

unevenness of the weld in width and height, as well as its deviations from the axis.

In especially damp rooms with a chemically active environment, the pipe fastening structures must be made of steel profiles with a thickness of at least 4 mm. Pipelines and fastening structures must be coated with protective varnish or paint.

Pipeline connections for open installation should be located outside walls, partitions, ceilings and other building structures of buildings.

Fastening pipelines to building structures buildings should be made with normalized supports and hangers. Welding of pipelines directly to metal structures of buildings and structures, as well as to elements of technological equipment is not allowed.

Welding of supports and hangers to building structures should be carried out without weakening their mechanical strength. Sagging and bending of pipelines are not allowed.

Each pipe bend over 0.5 m in length must be secured. The distance from the hangers to the welded and threaded pipe joints must be at least 100 mm.

Newly installed sprinklers must be cleaned of preservative grease and checked with a hydraulic pressure of 1.25 MPa (12.5 kgf / cm2) for 1 minute. Average term the service life of the sprinklers is defined for at least 10 years.

Instructions

for the operation of the automatic system station

water fire extinguishing

1. The procedure for determining the operability of the installation and external signaling of technological equipment during automatic and manual start-up.

2. Modes of operation of technological equipment in standby mode.

3. The order of action of the personnel on duty when taking over the duty.

4. Actions of the personnel on duty in the event of a fire.

5. The order of actions of the personnel on duty upon receipt of a signal about a malfunction of the installation.

1. Procedure for determining performance

installations and external signaling.

1.1. Auto mode

The fire extinguishing installation should operate in automatic mode, while the “Voltage at input No. 1” and “Voltage at input No. 2” lamps should be lit on the YS switchboard located in the fire station, and all other lamps should be off. In the control unit (pumping room) on the ShU switchboard, all lamps are off, the keys to control the operating mode of the main (No. 1) and backup (No. 2) pumps (on the ShN shield) must be in the "Automatic" position

1.2. Manual mode

During routine maintenance or at the request of the operation service, the installation can be switched to manual mode, while the lamps "Voltage at input No. 1", "Voltage at input No. 2", "Disabling the automation of the working pump" should be on on the YS switchboard in the fire station, "Disabling the automatic backup pump", in the control unit (pumping room) on the ShN switchboard, the keys for controlling the operating mode of the main (No. 1) and backup (No. 2) pumps must be in the "Manual" position and the lights "Disable automatic start of the working pump" are on, "Disable automatic start of the backup pump", all other lamps on the control panel are off.

2. Modes of operation of technological equipment

in standby mode.

Control unit (pumping station):

Above front door the "Fire extinguishing station" lamp is on

Pressure above the VS-100 valve according to the MP No. 1 manometer - not less than ___ atm.

The pressure in the pneumatic tank is not lower than ___ atm. according to EKM-2

Water level in the pneumatic tank at 1/2 of the sight glass

Gate valves No. 1,2,3,4,5,6,7,8 - open

Gate valves No. 9,10 - closed

Valves No. 1,2 - open

Valves No. No. No. 3.4,5,6,7 - closed

Leaks from the valve, valves should not be

Gate valves, gates and mode control keys must be sealed with seal No. 2 "Rubezh"

3. The order of the attendant at

interceding on duty.

The duty officer is obliged:

1. Make a bypass and perform an external inspection of the equipment and check the readings of the devices - "Fire post" (duty personnel), "Control unit (pumping room)", "Protected rooms" (duty electrician).

2. Make sure that the light and sound signaling is in accordance with paragraph 1.1 and paragraph 1.2.

3. Make sure that the operating modes of the process equipment are consistent. (electrician on duty)

4. Check the operation of light and sound alarms: (duty personnel)

A) press the button "Testing the light signaling" - all the lamps on the YS shield will light up, except for the reserve.

B) press the button "Fire signal testing" - the "Fire" lamp will light up and the roar will go off.

B) press the "Fault signal test" button - the "Fault" lamp will light up and the bell will ring.

5. Make entries in the "Log for monitoring the technical condition of the fire extinguishing installation" readings of the pressure gauge No. 1 and EKM No. 2. (electrician on duty) Perform rounds at 6.00, 12.00, 18.00, 24.00 hours.

4. The order of action of the personnel on duty in case of fire

Automatic sharp

In the event of a fire in the protected area (damage, destruction of the sprinkler), the automation is triggered and irrigates the fire. On the YS shield it is triggered light signaling: "Fire", and the howler turns on. With a further drop in pressure, EKM No. 2 is triggered and lamps on the YS shield light up: “Pressure drop in the impulse device” and “Malfunction”, “Start of the working pump” and a howler and a bell ring. If the working pump does not create pressure (it is faulty), the backup pump (No. 2) is automatically started and the "Start of the backup pump" lamp on the panel lights up. It is necessary to turn off the sound signals on the YS shield by switching the toggle switches.

Handcrafted sharp.

In the event of a fire in the protected area (damage, destruction of the sprinkler), the automation is triggered and irrigates the fire. On the YS shield a light alarm is triggered: "Fire", and a howler is turned on. It is necessary to turn off the sound signals on the YS switchboard by switching the toggle switches (duty personnel) to call the duty electrician.

The pumps are started from the "Control unit" (pumping room), when the keys for controlling the modes of the pumps (main and backup) on the ShN board are switched to the "Manual" position. Open the valve No. 1 under the BC-100 valve. The pump is started by pressing the "Start" button of one of the pumps. (electrician on duty)

After extinguishing the fire.

Transfer the keys for controlling the operating modes of the pumps in the "Control unit" (pumping room) on the ShN switchboard to the "Manual" position, if they were in the "Automatic" position, press the "Stop" buttons of both pumps. Close valve No. 1 under the BC-100 valve. (electrician on duty).

Representatives of a specialized organization must restore the system.

5. The order of action of the staff on duty when

receiving a "Fault" signal.

The "Fault" signal appears in the following cases:

Lack of voltage at one of the inputs;

Disabling automation;

Open circuit of SDU;

Decrease or absence of pressure in the impulse tank, while at the YS shield

the "Fault" light alarm is triggered and the bell rings.

Necessary:

1. Turn off the sound signaling and call the duty electrician (duty personnel)

2. Inform the person responsible for the operation of the water fire extinguishing installation, (electrician on duty)

3. Make an entry in the "Journal of malfunctions and operations of fire extinguishing and fire alarm", (electrician on duty)

4. Call the representatives of the service organization by phone.